Ground and wall fixation

  1. Mixer decommissioned.
  2. Operating space emptied, cleaned and, if required, disinfected.
  3. Mixer cleaned and, if required, disinfected.
  4. Ensure work is carried out by two persons.
  1. Disconnect mixer from the mains.
  2. Disconnect and wind up the connection cable.
  3. Enter the operating space. DANGER! If the operating space cannot be cleaned and disinfected, wear protective equipment according to work regulations!
  4. Uninstall mixer from the basin wall or the basin floor.
  5. Set the mixer down on a pallet, secure it against slipping and lift it out of the operating space.
  1. Removal is complete. Clean and disinfect the mixer thoroughly.